31.1 C
Cagayan de Oro
Tuesday, May 14, 2024
spot_img
More
    spot_imgspot_img

    Latest Posts

    Mountain Diversion Road cuts time from Uptown to airport by half

    Opol-El Salvador-Alubijid-Laguindingan Airport Mountain Diversion  Road, Cagayan de Oro City

    A new road cutting through the mountainous portion of Cagayan de Oro and West Misamis Oriental aims to cut travel time by half from the Uptown portion of the city to Laguindingan Airport and vice versa when it is completed by the end of 2024.

    Road alignment approaching Pueblo de Oro

    Implemented by DPWH Regional Office X with contractor Triparco Development Corporation as Project 23K00296, the four-to-six lane 35.89 kilometer Opol-El Salvador-Alubijid-Laguindingan Airport Mountain Diversion  Road, Cagayan de Oro City will reduce travel time from CDO Airport Road to Laguindingan from the usual one (1) hour and eleven (11) minutes to only thirty (30) minutes once it is completed by December, 2024.

    CDO Airport Road origin

    This road starts from CDO Airport Road (back of Hotel Koresco) thence towards the western side of Misamis Oriental passing through some western barangays of the city, and thence traversing the Municipality of Opol, City of El Salvador, the Municipalities of Alubijid and Laguindingan, Misamis Oriental.

    Six lane portion in Pueblo de Oro area

    The road segments vary from four to six lanes, like the Balubal-Indahag section has 2-lanes with provision for bike lanes, which expands to six lanes around the Amaya View and Pueblo de Oro sections, and eventually to four lanes in the Baikingon-Opol-El Salvador-Alubijid Laguindingan sections.

    Aside from opening up a new link to the Laguindingan Airport, the new road would also offer a short cut to Uptown Cagayan de Oro for travelers coming from Iligan City, Lanao del Norte, Lanao del Sur and the western coastal municipalities of Misamis Oriental.

    Panguil Bay Bridge

    Traffic over this particular road is expected to further multiply once the P7.3 billion 3.7 kilometer Panguil Bay Bridge opens to vehicular traffic by June 2024, thereby drastically cutting travel time Lanao Del Norte and Misamis Occidental from 2.5 hours by land to just 7 minutes, and expediting travel to Uptown Cagayan de Oro from the previously distant provinces of Misamis Occidental, Zamboanga del Norte and Zamboanga del Sur.

    Indicative road alingment (GFX by CDODev.com)

    Started in August 14, 2023, the Opol-El Salvador-Alubijid-Laguindingan Airport Mountain Diversion  Road, Cagayan de Oro City is funded  under GAA 2023 in the amount of P189,115,203.88 as shown in the Commission of Audit billboard for the said project.

    Photos taken by TRip ni ToniO earlier this month show the ongoing road opening works. (RMB with infographics courtesy of metrocdodev.com and photos by TRip ni ToniO.

    ####

    spot_img

    Latest Posts

    spot_imgspot_img

    Don't Miss

    spot_imgspot_img

    Stay In Touch

    Get updated with all the latest news, offers and special announcements.